Budget tip: get the safety assessment done BEFORE ordering the press. We ordered a press for a CE-marked line and then discovered we needed additional safety relays, a safety PLC upgrade, and modified guarding. Added $35K and 6 weeks to the project. If we'd done the assessment first, the vendor could have included it in the original package.